ISO 22301:2019
Rendered when the buyer ticks "ISO 22301:2019 (site continuity, standby lines only)". The register cites 5 of its 57 clauses, behind 0 findings, and on the rows of every supply point it reaches.
Requirement text quoted from the standards themselves, published at compliance.theartofservice.com, the same publisher as this register, read against the held text of each standard: our statement of each clause, not the instrument verbatim. Source framework: ISO 22301:2019. What it attaches to a supply point: the ISO 22301 regime page.
Clauses cited
5 of 57ISO 22301 8.1 Operational planning and controlPlan, implement and control the processes needed to meet BCMS requirements and to carry out the actions determined under risks and opportunities, by establishing process criteria, controlling the processes against those criteria and keeping enough documented information to be confident the processes ran as planned; control planned changes and review the consequences of unintended ones, taking mitigating action, and ensure outsourced processes and the supply chain are controlled.
Common gap: Supply chain control asserted through contract clauses with no verification behind them
Framework page: ISO 22301:2019
ISO 22301 8.2.2 Business impact analysisUse the impact analysis process to set continuity priorities and requirements: define the impact types and criteria relevant to the organization's context, identify the activities supporting delivery of products and services, assess impacts over time from disrupting those activities, fix the point at which non resumption becomes unacceptable, set prioritized time frames within that point for resuming activities at a specified minimum acceptable capacity, identify the prioritized activities, and determine the resources, dependencies and interdependencies they rely on including partners and suppliers.
Common gap: Recovery time frames set by aspiration and never reconciled to the impact analysis that should produce them
Framework page: ISO 22301:2019
ISO 22301 8.3.2 Identification of strategies and solutionsIdentify candidate strategies and solutions by the extent to which they meet the requirement to continue and recover prioritized activities within the identified time frames and agreed capacity, protect those activities, reduce the likelihood of disruption, shorten its duration, limit its impact on products and services, and provide for adequate resources.
Common gap: Candidates assessed on cost alone at the identification stage, collapsing identification into selection
Framework page: ISO 22301:2019
ISO 22301 8.4.4 Business continuity plansDocument and maintain business continuity plans that guide teams through response and recovery, collectively containing the actions to continue or recover prioritized activities within predetermined time frames, the means of monitoring the disruption and the response, the pre defined thresholds and process for activating the response, procedures to deliver products and services at agreed capacity, and how the immediate consequences are managed with regard to individual welfare, prevention of further loss and environmental impact; each plan must state purpose, scope and objectives, the roles and responsibilities of the implementing team, the actions implementing the solutions, the supporting information needed to activate, operate, coordinate and communicate including activation criteria, internal and external interdependencies, resource requirements, reporting requirements and a stand down process, and must be usable and available at the time and place it is needed.
Common gap: Plans that cover activation and response but have no stand down, so the organization never formally returns to normal
Framework page: ISO 22301:2019
ISO 22301 8.4.5 RecoveryMaintain documented processes to restore and return business activities from the temporary measures adopted during and after a disruption.
Common gap: Recovery treated as implicit once the incident is closed, with no process behind it
Framework page: ISO 22301:2019
See which clauses your list engages
Paste the list and every supply point names the clauses behind it, filtered to the regimes that apply to you. Eight supply points free, no account.
Build my energy register